This is a timeline of the new serviced office on the 11th floor of the SM Aura Office Tower. This page will feature weekly updates from the time it was a bare space until its grand launch. The new serviced office is slated to be open for business in April. If you are interested in this new serviced office fill up the quick contact form on the right or send us an email at info@kmcsolutions.us

 

May 14, 2014

The serviced office is now complete and operational. There are already several clients that have moved in and more are coming in. The whole project took around 3 months to complete and it is now officially KMC's largest serviced office.

April 11, 2014

The desk at the reception area has been installed. Finishing works are being done on light fixtures in the hallway and conference room. The large offices are ready for cleaning and carpeting. The server racks are being installed in the data center. The pantry has made progress with the paint almost done and some of the appliances delivered.

April 3, 2014

The new serviced office civil works is complete. The reception area is finished with the furniture to be installed. The large work floor is queued for finishing works such as cleaning and carpeting. Cabling is almost complete with finishing works to be done in a few offices and the training room. The pantry will be one of the last areas to be finished as there were some revisions in the design. The data centre has the raised floor completed and cabling completed. The new office is near the finish line!

March 27, 2014

Construction at the new serviced office is making progress. Structured cabling is now at 50% completion. The office's data center is starting to take shape. The doors have been installed and the cabinets for the pantry fabricated. The ceilings are now being closed up as structured cabling is progresses to completion and the air-conditioning units have been relocated. Just a few more weeks until the office is done!

March 19, 2014

After the 4th week of construction, civil works are 90% complete. The glass installations of all the offices have been completed. The finishing paint of all units are almost done. Doors have been made and are ready for installation. Air-conditioning units are also being relocated to their proper layout. Now, structured cabling has started and is at 35% completion. Cabling is expected to be finished by the end of March.

March 11, 2014

After 3 weeks, all the dry walls are complete and has primer paint as well. The construction of the reception area is ongoing with tiling almost complete. Manager's cabins in the large work floors are also up. Now structured cabling which is a vital part of the office has now started. At this point, the office is 30% complete.

March 4, 2014

After the 2nd week of construction, all dry walls and insulation have been completed and are being painted. JPM is now building the manager's cabin in the large work floors. The construction of the reception area is being built and tiling has also started.

February 26, 2014

After only 1 week, dry walls are up and insulation is being installed. Electrical and civil works are well under way. The ceiling is already being prepared for areas that will have fixtures.

February 19, 2014

This is the bare space of the 11th floor of the SM Aura Office Tower. Preparation was started and it will look like the 4 renders that were done by the contractor Javier Project Managers.