V Corporate Center Updates

  • COMPLETE. The offices are ready to be moved in to!
  • COMPLETE. The facility also has facilities with desks or cubicles.
  • COMPLETE. The pantry for clients to relax and eat.
  • Day 1. The bare space of the 9th floor of V Corporate Center. Soon to be the newest KMCS serviced office for 2014!
  • Week 1. Steel frames and panels are going up for the drywalls. Insulation is next.
  • Week 2. Insulation is being installed in the drywalls.
  • Week 3. Reception area is close to starting finishing works.

This is a timeline of our current serviced office on the 9th floor of the V Corporate Center. This page features weekly updates from the time it was a bare space until its grand launch. The 9th floor serviced office was completed on May 14, 2014. If you are interested in this serviced office, fill out the quick contact form on the right or send us an email at info@kmc.solutions

 

May 14, 2014

The serviced office is now complete. Some of the offices have been leased and the new tenants will be moving in soon. The whole project took 1 and a half months which was ahead of schedule.

April 11, 2014

Week 3 is done. Insulation is done and the walls are up. Cabling is on schedule and the server racks for the server room are being assembled. Glass will be installed for the meeting rooms and the details on the panel of the reception is done. Lighting fixtures are undergoing finishing works. Aircons have been relocated to their proper layout and the emergency systems such as smoke detectors and sprinklers are being relocated as well. The construction in V Corp is moving fast and businesses are starting to grab the best spots.

April 3, 2014

Week 2. Insulation is being installed. The tiling in the reception is being started. Cabling has also started. Construction at the new office is ahead of schedule!

March 27, 2014

Week 1. The steel frames are up and the panels are being placed. Insulation in the walls will be installed next. Ceiling panels have also been cleared as the contractor preps it for cabling and lighting works.

March 20, 2014

This is the bare space of the 9th floor of the V Corporate Center. Preparation was done such as taping the layout for the drywalls. The new office is slated to be completed by the end of May

 

 